The project incorporates private capital and technology. Rambaldi replicates the efficiency model that Milei's government promotes
Compartir:
The Municipality of La Calera began the refunctionalization of the Waste Transfer Center with an investment of 3.1 billion. The project seeks to align local management with technical efficiency standards through the active participation of private capital. The initiative breaks with years of administrative neglect and will directly benefit 60,000 residents in the northern area of Córdoba.
The awarding to the private firm Pablo Federico e Hijos S.A. introduces a market logic to solve a chronic structural problem. The new pressing technology will reduce the volume of garbage by 50%, achieving a significant saving in the system's final logistics. The objective is to put an end to the waste of resources caused by an obsolete system that punished the local taxpayer's pocket.
The processed waste will be transported in roll-off containers to the Piedras Blancas site for its final disposal in a safe manner. This operational scheme drastically reduces the number of trips needed, generating considerable fiscal savings for the municipality's coffers. The modernization of the plant makes it possible to professionalize the public service, guaranteeing quality standards that protect neighboring private property.
La Municipalidad de La Calera puso en marcha la refuncionalización del Centro de Transferencia de Residuos ubicado en el barrio Alto La Campana.
Efficient management and technology
Mayor Fernando Rambaldi emphasized that the project represents a cultural change toward an austere and professional administration of resources. The leader valued the synergy with the private sector to provide technical solutions without increasing the size of the municipal State. The decision aims to put the accounts in order through an intelligent investment that respects the fiscal effort of local residents.
The execution period for the work is set at 180 calendar days and includes paving the access roads for truck traffic. The plan also includes the technical treatment of leachate and odor control to guarantee the healthiness of the residents' surroundings. Safety in internal circulation and perimeter afforestation complete a comprehensive project that enhances the value of the land adjacent to the site.
El plazo de ejecución de los trabajos está estipulado en 180 días corridos e incluye la pavimentación de los accesos para el tránsito de camiones.
The authorities confirmed that a contingency plan remains active to ensure normal collection while civil works progress. The modernization of the site will make it possible to recover the area's value by eliminating the environmental liabilities that affected real estate development. This intervention demonstrates that collaboration between municipalities makes it possible to carry out large-scale works that improve cities' competitiveness.